A project manager is managing a project that is scheduled to take ten months to complete. The project is in its sixth month and $450,000 has been spent. The project budget is $990,000. Which of the following will the project manager use to determine the budgeted cost of work scheduled?
A.
Estimate to completion
B.
Planned value
C.
Cost performance index
D.
Budget at completion