The amount of time ahead or behind schedule on a project is called the:

The amount of time ahead or behind schedule on a project is called the:

The amount of time ahead or behind schedule on a project is called the:

A.
schedule baseline.

B.
schedule performance index.

C.
estimate to complete.

D.
schedule variance.