Which of the following will MOST likely increase?

A network diagram shows two critical paths for a project. Which of the following will MOST likely increase?

A network diagram shows two critical paths for a project. Which of the following will MOST likely increase?

A.
Staff

B.
Risk

C.
Cost

D.
Time