Which of the following should be the NEXT step?

A key stakeholder has asked the project manager to complete the project a week earlier than expected. To accomplish this objective, the project manager will have to ask the project team to work overtime, which will increase the cost of the project. Which of the following should be the NEXT step?

A key stakeholder has asked the project manager to complete the project a week earlier than expected. To accomplish this objective, the project manager will have to ask the project team to work overtime, which will increase the cost of the project. Which of the following should be the NEXT step?

A.
Ask the key stakeholder for more funding for the project.

B.
Ask the project team to work overtime to finish the project.

C.
Obtain an approved change control document before changing the project schedule.

D.
Agree to complete the project using the new schedule.



Leave a Reply 0

Your email address will not be published. Required fields are marked *