The project manager should update which of the following?

A project manager has to complete an asset inventory project for a large corporation. Several departments have refused to allow access to the equipment to complete the project. The project manager should update which of the following?

A project manager has to complete an asset inventory project for a large corporation. Several departments have refused to allow access to the equipment to complete the project. The project manager should update which of the following?

A.
Change control form

B.
Risk register

C.
Work Breakdown Structure (WBS)

D.
Issues log