A project manager has determined the probability and impact of identified project risks. A meeting with the project team will be held to determine how to mitigate risks above the project threshold. Which of the following will be created during this meeting?
A.
Risk response strategies
B.
Risk register
C.
Risk assessment
D.
Stakeholder risk tolerance