A project manager can create a risk breakdown structure (RBS) to determine which of the following?

A project manager can create a risk breakdown structure (RBS) to determine which of the following?

A project manager can create a risk breakdown structure (RBS) to determine which of the following?

A.
Risk tolerance

B.
Risk probability

C.
Risk category

D.
Risk impact