Which of the following documents should be updated?

The change control board approved a request for $25,000 to address rising labor costs of specialized trades. Which of the following documents should be updated?

The change control board approved a request for $25,000 to address rising labor costs of specialized trades. Which of the following documents should be updated?

A.
Scope statement

B.
Project schedule

C.
Resource requirements

D.
Project budget