This can MOST likely be attributed to:

An experienced team member comes to the project manager to report that they are uncertain of the project requirements. This can MOST likely be attributed to:

An experienced team member comes to the project manager to report that they are uncertain of the project requirements. This can MOST likely be attributed to:

A.
a poorly decomposed WBS.

B.
inadequate schedule analysis.

C.
inadequate resource management.

D.
improper risk planning.