To determine the MOST likely estimate for the length of project activities, a project manager would use which of the following?

To determine the MOST likely estimate for the length of project activities, a project manager would use which of the following?

To determine the MOST likely estimate for the length of project activities, a project manager would use which of the following?

A.
PERT

B.
Gantt chart

C.
WBS Dictionary

D.
SPI