Which of the following is the MOST common relationship used, when constructing a project schedule network diagram?

Which of the following is the MOST common relationship used, when constructing a project schedule network diagram?

Which of the following is the MOST common relationship used, when constructing a project schedule network diagram?

A.
Start-to-Finish

B.
Finish-to-Start

C.
Start-to-Start

D.
Finish-to-Finish



Leave a Reply 0

Your email address will not be published. Required fields are marked *