Which of the following would be the BEST tool to estimate the final duration?

A project team is estimating the amount of time needed to perform an activity. They have recommended an optimistic, pessimistic, and most likely duration to complete the activity. Which of the following would be the BEST tool to estimate the final duration?

A project team is estimating the amount of time needed to perform an activity. They have recommended an optimistic, pessimistic, and most likely duration to complete the activity. Which of the following would be the BEST tool to estimate the final duration?

A.
PERT

B.
GANTT

C.
GERT

D.
WBS



Leave a Reply 0

Your email address will not be published. Required fields are marked *