In which of the following situations would a risk be placed in the upper right quadrant of a risk matrix?

In which of the following situations would a risk be placed in the upper right quadrant of a risk matrix?

In which of the following situations would a risk be placed in the upper right quadrant of a risk matrix?

A.
The team identified a risk to have a medium probability of occurrence and a high impact on project success.

B.
The team identified a risk to have a high probability of occurrence and a high impact on project success.

C.
The team identified a risk to have a low probability of occurrence and a high impact on project success.

D.
The team identified a risk to have a high probability of occurrence and a medium impact on project success.