Which of the following can a project manager use to determine the critical path of a project? (Select Three).
A.
Business requirements
B.
Sequence of activities
C.
Completion date
D.
Stakeholder expectations
E.
Start date
F.
Risk register
Which of the following can a project manager use to determine the critical path of a project? (Select Three).
Which of the following can a project manager use to determine the critical path of a project? (Select Three).
A.
Business requirements
B.
Sequence of activities
C.
Completion date
D.
Stakeholder expectations
E.
Start date
F.
Risk register