Which of the following techniques could a project manager use to determine a project schedule based upon a variety of simulations?

Which of the following techniques could a project manager use to determine a project schedule based upon a variety of simulations?

Which of the following techniques could a project manager use to determine a project schedule based upon a variety of simulations?

A.
Schedule network analysis

B.
Critical chain method

C.
Critical path method

D.
Monte Carlo analysis