A project has a CPI of 0.6. Which of the following would BEST describe the cost-efficiency of the project?
A.
The costs are currently over the estimates.
B.
The costs and the estimates are about the same.
C.
The costs are currently under the estimates.
D.
The earned value is greater than the actual cost.