If the EV is $3,000 and the AC is $4,000, which of the following is the CV for the project?

If the EV is $3,000 and the AC is $4,000, which of the following is the CV for the project?

If the EV is $3,000 and the AC is $4,000, which of the following is the CV for the project?

A.
-$1,000

B.
$1,000

C.
-$3,000

D.
$3,000

E.
There would be a 25 percent cost decrease.

F.
There would be a 75 percent cost increase.

G.
The project is over-budget.

H.
The project is under-budget.