The project manager has documented a change request from a key project stakeholder. Which of the following actions should the project manager take NEXT?
A.
Discuss this change during the next status meeting.
B.
Ask other stakeholders for recommendations.
C.
Send the request to the change control board.
D.
Perform an impact analysis.