An adjustment to the project has been approved and funding granted, but the project manager feels the modification is out of scope.
Which of the following should the project manager do?
A.
Schedule a meeting with the project sponsor to reject the adjustment.
B.
Refuse to make the adjustment and send a recommendation to the review board.
C.
Make the adjustment and wait for another review.
D.
Make the adjustment but document the concern.