Which of the following is an appropriate risk response for diverting a portion of the project risk?
A.
Avoiding
B.
Sharing
C.
Enhancing
D.
Exploiting
Which of the following is an appropriate risk response for diverting a portion of the project risk?
Which of the following is an appropriate risk response for diverting a portion of the project risk?