A program manager informs a project manager that a new, high-priority project has been approved
and will need the current project’s resources before the scheduled project close- date The project
team meets and determines that the project should be fast-tracked. Which of the following
documents should the project team reference to fast-track the project? (Select TWO.)
A.
Scope management plan
B.
Configuration management plan
C.
Network diagram
D.
Project schedule
E.
Project plan