Which of the following should have occurred to prevent …

During the execution phase, the project manager discovered that the testing phase is dependent
on completion of the vendor’s tasks The project team has just informed the project manager their
activities are almost complete, and they would like permission to begin testing. The vendor is not
scheduled to deliver the products for two months. Which of the following should have occurred to
prevent this issue?

During the execution phase, the project manager discovered that the testing phase is dependent
on completion of the vendor’s tasks The project team has just informed the project manager their
activities are almost complete, and they would like permission to begin testing. The vendor is not
scheduled to deliver the products for two months. Which of the following should have occurred to
prevent this issue?

A.
During the planning phase, the project manager should have recognized the relationship between the vendor’s
and project team’s tasks and adjusted the schedule for the project team to begin activities two months later.

B.
The project manager should have crashed the schedule for the vendor to keep it at the same work pace as the
rest of the project team.

C.
During the project team’s regular status meeting with the vendor, the project team should have informed the
vendor that the team was ahead of schedule and to speed up their work.

D.
During the project team’s regular status meeting with the vendor, the vendor should have informed the project
team that it required another two months, and to slow down.



Leave a Reply 1

Your email address will not be published. Required fields are marked *


Jeremy ST

Jeremy ST

Congratulations!! Cleared the PK0-004 exam recently!!!

Scored 8xx/900 (the passing score is 710/900 now).

Got 95 questions (THE Maximum~~~LOL), including many MCQs and fill in the blank questions.

Around 30% questions are on Project Basics (Summarize, Classify, Compare and contrast…etc.), the primary knowledge of the Project+.

Also, many questions on Communication and Change Management (about 20%).

Pay close attention to the topic of “Project Tools & Documentation”, a little difficult, I feel.

Questions on this site are sure not enough for passing!

And, recommend you to use the PassLeader PK0-004 dumps for preparing for the test, all questions are from it.

Here, you can get the PL PK0-004 dumps for free:

http://www.comptiadump.com/category/comptia-project-plus-certification/pk0-004-dumps

Good Luck!!!