Due to a new government regulation, a project change is required. The project manager evaluates
the change and realizes a legal department will need to approve the change as well. The project
manager should ____.
A.
follow the change process flow and notify the legal department after the change is implemented
B.
extend a formal invitation to the legal department representative to join the CCB
C.
hold a separate meeting with the legal department representative and ask for approval
D.
notify the legal department representative in the event of an upcoming audit