Which of the following is MOST likely to be the first d…

A vendor has accepted a proposed project from a customer. Which of the following is MOST likely
to be the first document created by the project manager?

A vendor has accepted a proposed project from a customer. Which of the following is MOST likely
to be the first document created by the project manager?

A.
Project charter

B.
Project management plan

C.
Project statement of work

D.
Project schedule