Which of the following metrics demonstrates to a project manager if a project is overspending or
under spending?
A.
EAC
B.
BAC
C.
CPI
D.
ETC
Which of the following metrics demonstrates to a project manager if a project is overspending or
under spending?
Which of the following metrics demonstrates to a project manager if a project is overspending or
under spending?
A.
EAC
B.
BAC
C.
CPI
D.
ETC
Hi! Congratulations!!
Finally passed the PK0-004 exam few days ago!!!
Scored 8xx/900 (the passing score is 710/900 now).
I had 95 questions (THE Maximum~~~LOL), including many MCQs and fill in the blank questions.
Around 30% questions are on Project Basics (Summarize, Classify, Compare and contrast…etc.), the primary knowledge of the Project+.
Also, many questions on Communication and Change Management (about 20%).
Pay close attention to the topic of “Project Tools & Documentation”, a little difficult, I feel.
Questions on this site are sure not enough for passing!
And, recommend you to use the PassLeader PK0-004 dumps for preparing for the test, all questions are from it.
Here, you can get the PL PK0-004 dumps for free:
http://www.comptiadump.com/category/comptia-project-plus-certification/pk0-004-dumps
Good Luck!!!