Which of the following activities are associated with the closing phase of a project? (Select TWO.)

Which of the following activities are associated with the closing phase of a project? (Select TWO.)

A.
Risk mitigation

B.
Archiving of project documents

C.
Tracking of expenditures

D.
Lessons learned

E.
Quality assurance