Two team members have concluded that documentation is not required due to the size of the
current project. The project manager has encouraged them to align strictly within the process.
Which of the following conflict resolution techniques has the project manager utilized1?
A.
Smoothing
B.
Forcing
C.
Compromising
D.
Avoiding