A stakeholder is unaware of a project’s status. Which of the following documents should the project
manager consult to ensure a?stakeholders are notified of project changes? (Select TWO.)

A stakeholder is unaware of a project’s status. Which of the following documents should the project
manager consult to ensure a?stakeholders are notified of project changes? (Select TWO.)

A.
Status report

B.
Organizational chart

C.
RAO matrix

D.
Meeting minutes

E.
Communication plan