A project manager is assigned to a project and has not had a handover meeting with the previous
project manager. The new project manager is reviewing the percent of project completion, schedule
progress, and budget constraints. Which of the following documents should the project manager
use to obtain this information?

A project manager is assigned to a project and has not had a handover meeting with the previous
project manager. The new project manager is reviewing the percent of project completion, schedule
progress, and budget constraints. Which of the following documents should the project manager
use to obtain this information?

A.
Project schedule

B.
Balanced scorecard

C.
Issue log

D.
Status report