Which of the following is the NEXT step?

A project manager is justifying a required change with the associated impact on the project. Which
of the following is the NEXT step?

A project manager is justifying a required change with the associated impact on the project. Which
of the following is the NEXT step?

A.
Implementation

B.
Approval

C.
Validation

D.
Auditing