Which of the following should the project manager do t…

Ann, one of the affected stakeholders, feels that the project team has not been giving periodic
stakeholder updates and that her input has not been taken into account. Which of the following

should the project manager do to ensure stakeholder expectations are met?

Ann, one of the affected stakeholders, feels that the project team has not been giving periodic
stakeholder updates and that her input has not been taken into account. Which of the following

should the project manager do to ensure stakeholder expectations are met?

A.
Ensure that Ann is involved during the testing phase of the project so she can call out functional gaps

B.
Organize a walkthrough of the solution and ensure face-to-face updates occur every two weeks

C.
Escalate the issue to the project steering committee that Ann is criticizing the project quality

D.
Organize a requirements workshop to capture any gaps



Leave a Reply 0

Your email address will not be published. Required fields are marked *