A customer has requested additional features for an active project. Which of the following steps
should take place NEXT?
A.
Implement the requested changes.
B.
Evaluate the impact of the changes.
C.
Update all project documents.
D.
Submit the requested changes to the CCB.
Congrats!!
Completed the CompTIA Project+ PK0-004 exam last week!!!
Scored 8xx/900 (the passing score is 710/900 now).
Totally came across 95 questions (THE Maximum~~~LOL), including many MCQs and fill in the blank questions.
Around 30% questions are on Project Basics (Summarize, Classify, Compare and contrast…etc.), the primary knowledge of the Project+.
Also, many questions on Communication and Change Management (about 20%).
Pay close attention to “Project Tools & Documentation”, a little difficult, I feel.
Questions on this site are sure not enough for passing!
And, I do recommend you to use the PassLeader PK0-004 dumps for preparing for the test, all questions are from it.
Here, you can get the PL PK0-004 dumps for free:
http://www.comptiadump.com/category/comptia-project-plus-certification/pk0-004-dumps
Good luck, all!!!