Which of the following would be BEST suited to contribu…

A WBS is being developed for a project. Which of the following would be BEST suited to contribute
cost and time estimates for the project activities?

A WBS is being developed for a project. Which of the following would be BEST suited to contribute
cost and time estimates for the project activities?

A.
Project team members

B.
Project sponsor

C.
Project manager

D.
Project scheduler