A hardware failure affects a server in a datacenter. The server is critical to company operation, and
the hardware vendor is out of stock on the parts needed to repair the server. A network technician
suggests replacing it with a server from the warm site. Which of the following should the technician
do FIRST?
A.
Outsource a hardware-certified courier to move the server to the datacenter.
B.
Check the DRP and BCP and talk to the company stakeholders before making the decision.
C.
Unrack the server from the warm site and move it to the datacenter.
D.
Order the parts from the hardware vendor and notify affected users that the server will be down.