A company has had problems with their HVAC system being able to cool their datacenter as they
have grown. Which of the following could BEST be used to help reduce the load on the HVAC
system?
A.
Replacing the CAT5 cables with CAT6 cables
B.
Replacing traditional racks with water cooled racks
C.
Turning off non-critical application servers during non-business hours
D.
Taking the second power supplys out of non-critical servers