A part of the pre-installation plan is to __________ and to ____________.
A.
plan the installation
B.
verifying the name of the server
C.
check hardware compatibility with the operating system
D.
build the server
Explanation:
The pre-installation planning activities include the following:
1. Planning the installation
2. Verifying the installation plan
3. Verifying hardware compatibility with the operating system
4. Verifying power sources, space, UPS, and network availability
5. Verifying network protocols, naming conventions, and domain names
6. Verifying that all correct components and cables have been delivered
References:
Charles J. Brooks, Server+ Certification Exam Cram 2 (Exam SK0-002), QUE Publishing, Indianapolis, 2006, pp. 227-240.