Which of the following best describe the pre-installation planning activities? (Choose all that apply)
A.
Verifying the installation plan
B.
Verify tomorrow’s hardware, rather than the models currently available.
C.
Verifying hardware compatibility with the operating system.
D.
Verifying the budget involved.
Explanation:
The test taker should be able to conduct pre-installation planning activities. These activities include: Planning the installation; verifying the installation plan; verifying hardware compatibility with the operating system; verifying power sources, space, UPS, and network availability; verifying network protocols, naming conventions, and domain names; and verifying that all correct components and cables have been delivered.
References:
Charles J. Brooks, Server+ Certification Exam Cram 2 (Exam SK0-002), QUE Publishing, Indianapolis, 2006, pp. 227-240.