Which of the following indicates the ideal situation when new software can be installed on the production network?

Which of the following indicates the ideal situation when new software can be installed on the production network?

Which of the following indicates the ideal situation when new software can be installed on the production network?

A.
After the software has been received by the manufacturer, you can install it on the production network.

B.
After the software has been installed on a test system has been baselined.

C.
After you have taken a new baseline of the new software on a test system has been baselined, and compared pre-installation and post-installation baselines to verify that there are no negative repercussions should you install the new software on the production network.

D.
None of the above.

Explanation:
The best approach to take for installing new software is to first take a new baseline of the new software on a test system has been baselined, and compared pre-installation and post-installation baselines to verify that there are no negative repercussions should you install the new software on the production network References: Charles J. Brooks, Server+ Certification Exam Cram 2 (Exam SK0-002), QUE Publishing, Indianapolis, 2006, pp. 443-444.