Which of the following can be implemented?

The Chief Information Officer (CIO) wants to implement a redundant server location to which the
production server images can be moved within 48 hours and services can be quickly restored, in
case of a catastrophic failure of the primary datacenter’s HVAC. Which of the following can be
implemented?

The Chief Information Officer (CIO) wants to implement a redundant server location to which the
production server images can be moved within 48 hours and services can be quickly restored, in
case of a catastrophic failure of the primary datacenter’s HVAC. Which of the following can be
implemented?

A.
Cold site

B.
Load balancing

C.
Warm site

D.
Hot site

Explanation:
Warm sites provide computer systems and compatible media capabilities. If a warm site is used,
administrators and other staff will need to install and configure systems to resume operations. For
most organizations, a warm site could be a remote office, a leased facility, or another organization
with which yours has a reciprocal agreement.