This is an example of:

During a code review a software developer discovers a security risk that may result in hundreds of hours of rework. The security team has classified these issues as

low risk. Executive management has decided that the code will not be rewritten. This is an example of:

During a code review a software developer discovers a security risk that may result in hundreds of hours of rework. The security team has classified these issues as

low risk. Executive management has decided that the code will not be rewritten. This is an example of:

A.
Risk avoidance

B.
Risk transference

C.
Risk mitigation

D.
Risk acceptance



Leave a Reply 2

Your email address will not be published. Required fields are marked *

9 + 2 =


Mike

Mike

Risk avoidance

MilkChewy

MilkChewy

They have accepted the risk and decided to not to rewrite the code, so risk acceptance