Which of the following is being tested when a company’s…

Which of the following is being tested when a company’s payroll server is powered off for eight hours?

Which of the following is being tested when a company’s payroll server is powered off for eight hours?

A.
Succession plan

B.
Business impact document

C.
Continuity of operations plan

D.
Risk assessment plan

Explanation:
Continuity of operations plan is the effort to ensure the continued performance of critical business functions
during a wide range of potential emergencies.



Leave a Reply 0

Your email address will not be published. Required fields are marked *

8 + eleven =