What is the correct order of the steps below to successfully complete this procedure?

Typically, when you upgrade the Security Management Server, you install and configure a fresh R75 installation on a new computer and then migrate the database from the original machine. What is the correct order of the steps below to successfully complete this procedure?

1) Export databases from source.

2) Connect target to network.

3) Prepare the source machine for export.

4) Import databases to target.

5) Install new version on target.

6) Test target deployment.

Typically, when you upgrade the Security Management Server, you install and configure a fresh R75 installation on a new computer and then migrate the database from the original machine. What is the correct order of the steps below to successfully complete this procedure?

1) Export databases from source.

2) Connect target to network.

3) Prepare the source machine for export.

4) Import databases to target.

5) Install new version on target.

6) Test target deployment.

A.
6, 5, 3, 1, 4, 2

B.
3, 1, 5, 4, 2, 6

C.
5, 2, 6, 3, 1, 4

D.
3, 5, 1, 4, 6, 2



Leave a Reply 6

Your email address will not be published. Required fields are marked *


Paul B

Paul B

Answer D suggests testing target deployment BEFORE it’s connected to the network! Could be tricky!

I think it should be B

Casbot

Casbot

I think B makes more sense too. Why would you do #3, then go and install the new machine, rather than doing #3 and then #1. Makes more sense to prepare the source machine for export and then do the export.

The problem is, how is Checkpoint looking at this. Any other thoughts?

Tony Unit

Tony Unit

The answer is definitely D.

The testing of the target deployment is with relation to confirming the migrate import is successful and the SMS is ‘working’, i.e. cpd and fwm look ok.

You then connect it to the network, and disconnect the old one, to confirm connectivity (SIC) to the gateways etc.

Tobias

Tobias

Answer D:
Install and Upgrade Guide R75 Section “Migration Workflow”
(R75.40 page 121)

ACP

ACP

Its D,

Installation and Upgrade Guide R77 | page:174

Trololo

Trololo

D.

From upgrade guide.
Migration Workflow
1. Prepare the source Security Management Server for export.
2. Install the R77 Security Management Server or a standalone deployment on the target server.
3. Export the management database from source Security Management Server.
4. Import the management database to the target Security Management Server.
5. Test the target deployment.
6. Connect the target Security Management Server to the network.