Your primary SmartCenter Server is installed on a SecurePlatform Pro machine, which is also a
VPN-1 Power Gateway. You want to implement Management High Availability (HA). You have a
spare machine to configure as the secondary SmartCenter Server. How do you configure the new
machine to be the standby SmartCenter Server?
A.
Use cpprod_util to reconfigure the primary SmartCenter Server to become the secondary on
the VPN-1 Power Gateway. Install a new primary SmartCenter Server on the spare machine and
set to “standby”. Synchronize the “active” secondary to the “standby” primary in order to migrate
the configuration.
B.
Install the secondary Server on the spare machine. Add the new machine to any network
routable to the primary Server. Synchronize the machines.
C.
You cannot configure Management HA, when either the primary or secondary SmartCenter
Server is running on a VPN-1 Pro Gateway.
D.
Install the secondary Server on the spare machine. Add the new machine to the same network
as the primary Server. Synchronize the machines.