The client has decided that Quality and Discrete Manufacturing will be implemented at a future
stage, so new supply from current manufacturing will be added to current inventory on hand by the
Open Transactions Interface. The immediate requirement is to go-live with Inventory and Order
Management. Which three seeded transaction types can be omitted for material status control?
(Choose three.)
A.
average cost update
B.
all internal transactions
C.
backflush subinventory transfer
D.
miscellaneous issues and receipts
E.
all transaction types related to Work in Process
F.
all transaction types related to Project Manufacturing
Explanation: