Which start event is allowed in a subprocess?

Which start event is allowed in a subprocess?

Which start event is allowed in a subprocess?

A.
Timer Start Event

B.
Boundary Event

C.
Message Start Event

D.
None Start Event

Explanation:
In Oracle BPM, subprocesses are embedded subprocesses. Subprocesses are
contained as part of the parent subprocess. Subprocesses must begin with a none start event and
must end with a none end event.
Reference: Oracle Fusion Middleware Business Process Composer User’s Guide for Oracle
Business Process Management, 11g Release 1 (11.1.1.5.0), 6 Modeling Business Processes with
Oracle BPM