Which two statements are true?

Which two statements are true? Select two.

Which two statements are true? Select two.

A.
In Oracle BPM 11g, a BPMN process can have only one start and one end event.

B.
A process started with a Timer Start Event can end with a message end event.

C.
A None Start Event is required when using a Human task of Initiator type to start a process.

D.
A Timer Start Event is used to automatically initiate a new instance of a process.

Explanation:
Oracle BPM supports the following ways of triggering a process instance:
* Using a message, signal, or timer start event.
* Using a none start event followed by a receive task. The receive task must be configured to
create a process instance.
* Using a none start event followed by a user task defined with the initiator pattern. (C)
* Using an event-based gateway that is configured to create a new process instance.
D: The timer start event triggers the creation of a process instance based on a specific time
condition.
Reference: Oracle Fusion Middleware Business Process Composer User’s Guide for Oracle
Business Process Management, 11g Release 1 (11.1.1.5.0), 6 Modeling Business Processes with
Oracle BPM



Leave a Reply 0

Your email address will not be published. Required fields are marked *