Your customer is Interested In Implementing revision control for the finished goods model Items.
Which two requirements can be met by implementing revision control? (Choose two.)
A.
Changing model functionality when on-hand quantity is available
B.
Tracking design changes in other modules (BOM, Work In Process) with a different model
number
C.
Scrapping the old model and introducing a new model which has changes in functionality and
features
D.
Accommodating a slight design change in the model, where functionality and features remain
the same
E.
Tracking design changes in all other functions, such as Bill of Materials, Routings, Work in
Process, and so on, using the same model number
Explanation: