Which task would you recommend before using the Database Upgrade Assistant (DBUA) to
upgrade a single-instance Oracle 11g R2 database to Oracle Database 12c?
A.
shutting down the database instance that is being upgraded
B.
executing the catctl.pl script to run the upgrade processes in parallel
C.
running the Pre-Upgrade Information Tool
D.
copying the listener.ora file to the new ORACLE_HOME
Explanation:
http://docs.oracle.com/cd/E11882_01/server.112/e23633/upgrade.htm#UPGRD12395
Refer – http://docs.oracle.com/cd/E18283_01/server.112/e17120/schema003.htm#CBBBIADA, Shrinking Database Segments Online
The correct answer will be enable row movement.
Sorry this comment is for Q. 150
C
Little tricky question, DBUA runs Pre-Upgrade tool as one of its steps. However Oracle recommends to run the tool before starting DBUA to run the tool ahead of time in order to analyze the database and take actions that can decrease downtime for upgrading.
BTW expl. link leads to 11g not 12c, there is the correct one:
http://docs.oracle.com/database/121/UPGRD/upgrade.htm#i1011482
C is correct one.
C
C
DVLA Number Plates