You work as a senior project manager in SoftTech Inc. You are working on a software project
using configuration management. Through configuration management, you are decomposing the
verification system into identifiable, understandable, manageable, traceable units that are known
as Configuration Items (CIs). According to you, which of the following processes is known as the
decomposition process of a verification system into Configuration Items?
A.
Configuration auditing
B.
Configuration identification
C.
Configuration status accounting
D.
Configuration control
Explanation: