You are the project manager for a construction project. The project involves casting of a column in
a very narrow space. Because of the lack of space, casting is highly dangerous. High technical
skill will be required for casting that column. You decide to hire a local expert team for casting that
column. Which of the following types of risk response are you following?
A.
Transference
B.
Mitigation
C.
Avoidance
D.
Acceptance
Explanation: